A batching plant does not usually fail all at once. A weigher drifts, a gate seal leaks slurry, a skip rope frays, and the plant gets slower and less accurate until something stops it. This is the service routine Schwing Stetter teaches plant crews, set out by the hour meter.
Ten habits that protect the plant
Before the schedule, these are the points the manufacturer asks every plant owner to hold to.
- Calibrate the weighers for cement, water, aggregate and admixture regularly, at least once a month.
- Chip and clean the mixer daily. Dry concrete left inside breaks off into later batches and reaches the transit mixer and the pump. A clean mixer also runs on less load.
- Clean the skip bucket regularly, above all in the rainy season, when wet fine aggregate sticks to it.
- Clean the mixer breathing hoses daily so the mixer can breathe freely.
- Keep the mixer discharge gate sealing properly. A poor seal loses slurry while mixing.
- Clean the cement and water butterfly valves and check them for leaks.
- Give the concrete enough mixing time.
- Ground the electrical equipment twice over.
- Use good raw materials.
- Start from a good mix design.
Every day
- Check the input voltage and the electrical connections.
- Check the mixer gearbox oil level.
- Check that the butterfly valves operate correctly.
- Check the air compressor oil level. Drain the condensate from the compressor tank and the water separator.
- Check that every screw conveyor runs properly.
- Check the safety limit switches on the mixer cover and the skip overrun.
- Check that the indicators and the emergency stop switches work.
- Look over the plant for anything abnormal: leaks, noise, loose parts.
- Check the mixer and its mixing elements for setting and condition.
- Check the condition of the skip rope, and the scraper rope where a scraper is fitted.
Every 50 hours
- Grease the pan mixer gate bearings, aggregate gate journals, skip slack-rope adjuster bushings, discharge gate cylinder mountings, screw conveyor hanger bearings, mixer loading gate journal bearings and the skip rope mounting journal.
- Grease the mixer arm bearing journals and check the condition of the springs.
- Clean the air compressor filter and fill the lubricator in the pneumatic circuit with oil.
- Check the oil level in the screw conveyor, skip and scraper gearboxes.
- Clean dust off the skip roller pathway.
- Clean and oil the weigher tie rod pins and the aggregate gate cylinder pins so they stay free.
- Clean the tie rod threads, grease them and cover them with plastic sheet so they can be adjusted when needed.
Every 100 hours
- Repeat the 50-hour work.
- Where a scraper is fitted, grease its rotation flange, shaft bushings and rollers.
- Clean the mixer breather pipe. A choked breather pipe makes the weigher readings erratic.
- Look over the plant again for anything abnormal.
Every 200 hours
- Repeat the 50-hour and 100-hour work.
- Calibrate all the weighers.
- Replace the air compressor lubricating oil and clean its filter.
- Check every pneumatic hose for condition and every pneumatic valve for leaks.
- Clean the cooling ribs of all the electric motors so they shed heat properly.
- Lubricate the skip bucket wire rope.
- On a belt conveyor, remove the journal caps, replace the grease and refit them.
- Clean the cement silos monthly and remove any set cement or foreign material.
Every 1,000 hours
- Repeat all the work above.
- Replace the mixer hydraulic filter and oil, where the mixer has a hydraulic system.
- Change the gear oil in the screw conveyor, belt conveyor, skip winch and scraper gearboxes.
- Check the skip bucket for wear.
- Check the mixing elements, particularly the arms, for wear and recondition them if necessary. Check the springs.
- Replace the skip bucket wire ropes if they are worn, and replace them as a pair.
- Replace the mixer gate sealing element so slurry does not leak during mixing.
Every 2,000 hours
- Repeat all the work above.
- Remove the mixer gate and check its bearings and journals. Replace the bearings and recondition the journals if they are worn.
- Check the mixer liner plates and replace them if necessary. The manufacturer gives 50,000 cubic meters of output as the reference point.
- Recondition the skip bucket if it shows wear.
- Check the aggregate gates for wear and recondition them.
For the electrical side of the plant, see powering a batching plant.