Skip to Content

Why your batching plant makes less than its rated output, and how to get it back

November 18, 2026 by

A batching plant sold as 112 m³ an hour does not always deliver 112. The rated figure is real, but it is measured under standard conditions with nothing slowing the cycle. On site, a loader that arrives late or a gate jammed by an oversize stone quietly takes concrete off every hour. Here is how the rated figure is worked out, how to measure your own, and where the missing output usually goes.

5.9 minfor 10 m³ on an M 2.5 at its rated 112 m³/hr
6.5 minfor the same 10 m³ in the worked example below
92.3 m³/hrwhat that half-minute difference leaves you with
Stetter batching plant with an inclined aggregate conveyor and four cement silos
Output depends on the whole chain: how aggregate reaches the plant, how fast cement and water arrive, and how quickly trucks get under the mixer.

What the rated output means

Every plant has a cycle diagram: the planned time for weighing aggregate, cement and water, lifting the batch, mixing and discharging. The rated output is that cycle repeated for an hour under standard conditions, with a standard mix of 300 kg of cement per m³ and no faults or alarms. For the Stetter M 2.5 the diagram gives 5.9 minutes to produce 10 m³, which is 112 m³ an hour.

How to measure your real output

You do not need a stopwatch. The batch sheet already has the answer.

  1. Pick a run of consecutive batches, for example one 10 m³ truck load.
  2. Note the start time of the first batch and the end time of the last.
  3. Divide the volume by the time taken.

In one example the load started at 10:42:05 and finished at 10:48:35. That is 6 minutes 30 seconds for 10 m³, or 92.3 m³ an hour, on a plant rated at 112.

SAME PLANT, SAME MIX Rated output against what the batch sheet shows Rated, standard conditions 10 m³ batched in 5.9 minutes 112 m³/hr Measured on site 10 m³ batched in 6.5 minutes 92.3 m³/hr 19.7 lost 36 seconds slower on every 10 m³ adds up to about 158 m³ less concrete over an 8-hour shift.

Where the output goes

Feeding the plant

  • Aggregate arrives in bursts, because the loader or tipper cannot keep the feeding conveyor or ramp supplied
  • The loader is too small for the plant
  • The stockpile is too far from the receiving hopper
  • Trucks are slow to get into position under the mixer

The materials and the mix

  • Oversize stones in the sand or gravel jam the discharge gates and stop the cycle while they are cleared
  • Richer, high-grade mixes need more cement per batch, so cement weighing takes longer and the plant reports that the cement batching time is exceeded
  • Slow water supply does the same for water batching
  • Aggregate quantity, water-cement ratio and concrete weight all change the cycle

The condition of the mixer

  • Mixing shovels and blades out of adjustment
  • Build-up on the discharge hopper and the mixer discharge gate
  • Hardened concrete inside the mixer that has not been chipped out

The people at the panel

  • Operators who accept tolerances, faults and alarms without understanding what they mean
  • Output worked out the wrong way, so nobody sees the gap
If cement is what holds the batch up, look at the screw conveyor. A 168 mm screw delivers about 22 tonnes an hour, a 219 mm screw about 60, a 273 mm screw about 100. For high-grade concrete, the larger screw is what keeps the cycle on time.
Stetter batching plant with in-line aggregate bins feeding the mixer tower
An in-line silo keeps more aggregate ready to batch, so the plant is not waiting on the loader between loads.

Two figures worth knowing on any spec sheet

  • Mixer size is quoted twice. A mixer listed as 525 / 350 liters takes 525 liters of dry material and gives 350 liters of compacted concrete. The filling volume is always 1.5 times the batch you get out.
  • Weighing capacity sets the richest mix. The cement scale limits how much cement can go into one batch, and so how strong a mix the plant can produce at full batch size.

Related

Is your plant below its rated output?

Send us a batch sheet and the plant model, and we will tell you where to look first.

Send a batch sheet
in Blog
PTO drive or drum engine? How to choose the drive for a transit mixer
Message usClose
Schwing Stetter PhilippinesChat with us on Messenger

Hello. Tell us which equipment or parts you need, and where your project is. We will reply on Messenger.

Opens Messenger with your message ready to send.