Skip to Content

How to lay and support a concrete delivery line

November 17, 2026 by

A delivery line is under more load than it looks. Every meter of it holds about 30 kg of concrete, and the pump pushes on that with tens of tonnes of force, stroke after stroke. A line that is laid and anchored well gives you a quiet, uninterrupted pour. One that is not gives you leaking couplings, blockages at the bends and pipes that walk across the slab.

230 kNthe most an SP 3000 D can push on the line
Every floorwhere a vertical line needs a support
Both sidesof each coupling on the base line
Large radiusfor the bend from horizontal to vertical

Start at the pump

Concrete pressure is highest in the first few meters, so this is where supports matter most. As an example, an SP 3000 D can put up to 230 kN, roughly 23 tonnes, onto the pipe.

  • Put the first pipe after the taper on a concrete block. The block takes the push so the pump does not have to.
  • Line the pump outlet up with the blocks. The valve housing at the back of the pump should carry no vertical load from the pipe.
  • Fit a shut-off valve near the pump on tall jobs. It lets you hold the concrete in the riser while you work on the pump.
  • Support the line rigidly at the reducer. Where the line steps down from 150 to 125 mm the force on the pipe is at its greatest.
Drawing of a stationary concrete pump with a straight delivery line anchored on a concrete block
The first run from the pump, anchored on a concrete block.

The base line: from the pump to the riser

The horizontal run between the pump and the vertical line takes the full pressure for the whole pour. Support it before and after every coupling, so no joint is left carrying the weight or the movement.

A double U-bolt pipe support on a steel base
A double U-bolt support for a horizontal line.
A pipeline coupling with a support on each side
A support on each side of the coupling keeps the joint free of load.
A delivery line running along a concrete footing with regular clamps
A base line carried on a continuous footing, clamped at regular intervals.
A delivery pipe clamped to a concrete block in a tunnel
Clamped down to a concrete block, so the pipe cannot lift or shift.

Bends

  • Fix every bend on its own. A bend is where the concrete changes direction, so it is where the line tries hardest to move.
  • Use a large-radius elbow from horizontal to vertical. This is the most likely place for a blockage, and a gentle bend keeps the risk as low as it can be.
  • Use small-radius elbows only between two horizontal runs or two vertical runs.

The riser

Support the vertical line at every floor. This carries the weight of the pipe and the concrete in it, and it stops the line from moving with each stroke.

A vertical delivery pipe clamped to a steel channel across a floor opening
A riser clamped to a steel channel where it passes through the floor.
A delivery line laid along a floor slab and tied back with chains
On the slab, the line is tied back so it stays where it was laid.

Lay it without stress

Pipes should meet squarely and sit naturally in their supports. A pipe that has been forced into line puts a side load on the coupling. That opens the seal, paste leaks out, and a leaking joint is where blockages begin.

Feeding more than one area

On a large floor you do not have to break down the whole line to move to the next pour.

  • A flip-over bend. A 90 degree bend at the end of the line feeds one area. When that area is finished, the bend is unclamped, turned over and connected to the next line, and pumping starts again.
  • A two-way switch bend. One incoming line can feed either a line on the same level or a line going up to the next floor, by swinging a single bend.
A delivery line with a bend laid across an open floor slab
A line with a bend on the slab. Changing which way the bend points changes which area is fed.

Long horizontal runs

In tunnels and on sites the pump cannot get close to, the line may run for hundreds of meters. The same rules apply over the whole length: regular supports, firm anchoring at each change of direction, and joints that carry no load.

A long delivery line running along the wall of a tunnel on regular supports
A long line carried on regular supports along a tunnel wall.
Before the first pour, walk the line. Every bend fixed, a support at every floor, a support on both sides of each coupling on the base line, and the first pipe on its block.

Planning a pipeline?

Send us the height, the run and a sketch of the layout.

Send your layout

See the Schwing stationary pumps

in Blog
What makes concrete pumpable, and why pipelines block
Message usClose
Schwing Stetter PhilippinesChat with us on Messenger

Hello. Tell us which equipment or parts you need, and where your project is. We will reply on Messenger.

Opens Messenger with your message ready to send.